Prince2-Practitioner Dumps

PRINCE2 Prince2-Practitioner Exam Dumps PDF

PRINCE2 Practitioner Exam

Total Questions: 282
Update Date: May 10, 2024

PDF + Test Engine $65
Test Engine $55
PDF $45

  • Last Update on May 10, 2024
  • 100% Passing Guarantee of Prince2-Practitioner Exam
  • 90 Days Free Updates of Prince2-Practitioner Exam
  • Full Money Back Guarantee on Prince2-Practitioner Exam

DumpsFactory is forever best for your PRINCE2 Prince2-Practitioner exam preparation.

For your best practice we are providing you free questions with valid answers for the exam of PRINCE2, to practice for this material you just need sign up to our website for a free account. A large bundle of customers all over the world is getting advantages by our PRINCE2 Prince2-Practitioner dumps. We are providing 100% passing guarantee for your Prince2-Practitioner that you will get more high grades by using our material which is prepared by our most distinguish and most experts team.

Most regarded plan to pass your PRINCE2 Prince2-Practitioner exam:

We have hired most extraordinary and most familiar experts in this field, who are so talented in preparing the material, that there prepared material can succeed you in getting the high grades in PRINCE2 Prince2-Practitioner exams in one day. That is why DumpsFactory available for your assistance 24/7.

Easily accessible for mobile user:

Mobile users can easily get updates and can download the PRINCE2 Prince2-Practitioner material in PDF format after purchasing our material and can study it any time in their busy life when they have desire to study.

Get Pronto PRINCE2 Prince2-Practitioner Questions and Answers

By using our material you can succeed in PRINCE2 Prince2-Practitioner exam in your first attempt because we update our material regularly for new questions and answers for PRINCE2 Prince2-Practitioner exam.

Notorious and experts present PRINCE2 Prince2-Practitioner Dumps PDF

Our most extraordinary experts are too much familiar and experienced with the behaviour of PRINCE2 Exams that they prepared such beneficial material for our users.

Guarantee for Your Investment

DumpsFactory wants that their customers increased more rapidly, so we are providing to our customer with the most demanded and updated questions to pass PRINCE2 Prince2-Practitioner Exam. You can claim for your investment by using our money back policy if you have not been availed with our promised facilities for the PRINCE2 exams. For details visit to Refund Contract.

Question 1

Which of the following statements is NOT correct?The Learn from Experience principle suggests that lessons should be actively sought...

A. When Starting a Project
B. When Initiating a Project
C. As the project progresses
D. As the project closes

Answer: B

Question 2

It is now late October and the project is in stage 3. The label design competition has been held and the photosof the staff have been taken. The CEO and Marketing Director still need to choose the winning label designand the 12 photos for the calendar. However, the Executive has learned that two competitors are issuingcalendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of theoptions the Project Manager has presented to the Project Board is to close the project prematurely.There are a number of key facts relating to this project that would need to be recorded if the project Y-e to beclosed now.Which product should show that the project has been closed prematurely and has not achieved the objectivesdefined in the Project Initiation Documentation (PID)?

A. Benefits Review Plan
B. End Project Report
C. Exception Report
D. Project closure notification

Answer: B

Question 3

It is now late October and the project is in stage 3. The label design competition has been held and the photosof the staff have been taken. The CEO and Marketing Director still need to choose the winning label designand the 12 photos for the calendar. However, the Executive has learned that two competitors are issuingcalendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of theoptions the Project Manager has presented to the Project Board is to close the project prematurely.There are a number of key facts relating to this project that would need to be recorded if the project Y-e to beclosed now.Which product should show that without the calendar the company is going to experience difficultiesrecovering its decline in orders, and alternative solutions are required if the company is going to recover itsposition?

A. Benefits Review Plan
B. Exception Report
C. End Project Report
D. Risk Register

Answer: C

Question 4

It is now late October and the project is in stage 3. The label design competition has been held and the photosof the staff have been taken. The CEO and Marketing Director still need to choose the winning label designand the 12 photos for the calendar. However, the Executive has learned that two competitors are issuingcalendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of theoptions the Project Manager has presented to the Project Board is to close the project prematurely.There are a number of key facts relating to this project that would need to be recorded if the project Y-e to beclosed now.Which product should show that the staff photo sessions were disruptive to the Engineering Department asthey had been scheduled during peak work times without consultation with the Engineering Manager?

A. Follow-on action recommendations
B. Lessons Report
C. Project closure notification
D. Risk Register

Answer: B

Question 5

It is now late October and the project is in stage 3. The label design competition has been held and the photosof the staff have been taken. The CEO and Marketing Director still need to choose the winning label designand the 12 photos for the calendar. However, the Executive has learned that two competitors are issuingcalendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of theoptions the Project Manager has presented to the Project Board is to close the project prematurely.There are a number of key facts relating to this project that would need to be recorded if the project Y-e to beclosed now.Which product should show that if anybody has any remaining resource costs to be charged to the project, theyshould ensure this is done by 10 November?

A. Benefits Review Plan
B. End Project Report
C. Follow-on action recommendations
D. Project closure notification

Answer: D

Question 6

Which of the following principles describes this statement?"xxx defines tolerances for each project objective to establish limits of delegated authority"

A. Manage by stages
B. Focus on products
C. Manage by exception
D. Learn from experience

Answer: C

Question 7

Which of the following statements is FALSE regarding the Continued Business Justification?

A. The justification for the project must remain the same throughout the project
B. The justification for the project should remain valid
C. The justification for the project may change
D. If the project is no longer justified it should be stopped

Answer: B

Question 8

It is now late October and the project is in stage 3. The label design competition has been held and the photosof the staff have been taken. The CEO and Marketing Director still need to choose the winning label designand the 12 photos for the calendar. However, the Executive has learned that two competitors are issuingcalendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of theoptions the Project Manager has presented to the Project Board is to close the project prematurely.There are a number of key facts relating to this project that would need to be recorded if the project Y-e to beclosed now.Which product should register that the risk of a competitor producing a calendar at the same time was identified at the beginning of the project but the assessment of this risk appears to have been poor?

A. Issue Register
B. Follow-on action recommendations
C.Lessons Report
D. Risk Register

Answer: C

Question 9

It is now late October and the project is in stage 3. The label design competition has been held and the photosof the staff have been taken. The CEO and Marketing Director still need to choose the winning label designand the 12 photos for the calendar. However, the Executive has learned that two competitors are issuingcalendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of theoptions the Project Manager has presented to the Project Board is to close the project prematurely.There are a number of key facts relating to this project that would need to be recorded if the project Y-e to beclosed now.Which product should show that the photos could be used for other promotional material for the company?

A. Benefits Review Plan
B. Lessons Log
C. Exception Report
D. End Project Report

Answer: D

Question 10

Which of the following principles uses Product Descriptions to provide clarity by defining each product'spurpose, composition, derivation, format, quality criteria and quality method?

A. Tailor to suit the project environment
B. Focus on products
C. Manage by stages
D. Continued business justification

Answer: B